ϼ

NEWS

Lindy’s Diner owners sue city over Bliss Building demolition

Owners allege city officials rushed the demolition of the 120-year-old Bliss Building without due process

The owner of the Bliss Building, Steve Vatoseow, stands across Central Avenue in Downtown on July 3 as the structure was demolished by the city. For decades, the property and its anchor tenant, Lindy’s Diner, served as a staple in the area but a recent collapse doomed the building to destruction. As a crane operator began to tear down what walls remained, the owner, Steve Vatoseow, watched from across the street. Vatoseow recently told the Journal the partial collapse and subsequent demolition of the century-old building has been “devastating in every way.”
Published Modified

The owners of the now-defunct Lindy’s Diner have sued the city of Albuquerque for its handling of the demolition of the historic Bliss Building.

Attorney Michael Cadigan, representing Lindy’s Diner owners Steve and Dawn Vatoseow, alleges the city did not need to demolish the building and rushed the Vatoseows into doing so.

The lawsuit was filed in 2nd Judicial District Court in Albuquerque on Sunday.

“The Bliss Building was fixable, but the City of Albuquerque demanded that the building be demolished, repeatedly giving the owners varying and conflicting timelines to complete the work,” the suit states.

In a Monday statement sent to the Journal, the city said it gave the Vatoseows time to address the situation and make whatever decision fits them.

“The City understands the historic importance of Lindy’s and the impact of losing the Bliss Building, but when a building becomes a threat to public safety, we act,” wrote a city spokesperson. “We made the difficult decision to remove the unsafe structure to protect downtown businesses, residents, and visitors who use Central Avenue and 5th Street every day.”

Demolition began on the Bliss Building roughly two months after a portion of the historic building crumbled in late April, leaving a slew of debris and building materials in its wake.

State Farm, the building’s insurer that provided coverage for seven years, is also being sued. The complaint alleges the insurance company was aware of the 120-year-old Bliss Building’s age and condition and still provided coverage, only to later deny claims that the Vatoseows filed.

 It is unclear if State Farm has an attorney yet.

Cadigan, a former city councilor who served from 2001 to 2009, including one term as city council president, said that city officials denied the Vatoseows due process by denying the family the time to make a decision or consider other options before demolishing the building.

"The government can't decide that your house needs to be torn down because it's not safe and not give you any due process rights,” he said. 

He added that the city rushed the process due to the Bliss Building’s location and because of the Route 66 Centennial, which has brought various events to the area.

“The most shocking thing that I think the city did in this is they just ignored state law and their own city law on how you condemn a building,” Cadigan said. "There was a political decision to tear it down and damn the torpedoes, full speed ahead.”

“I understand that this is downtown and the Route 66 festival is coming up, but it's an interesting question,” he added. “If this building had been at the corner of Eubank and Lomas, would the city have acted like this?”

The demolition timeline

Demolition on the building began June 30 after officials announced that the city would begin the process of razing the building after the Vatoseows "failed to follow through on their promise to demolish the collapsing building,” states a June 30 news release.

Officials said the city chose to step in after it became “clear that they are unwilling or unable” to perform the deconstruction of the Bliss Building in what the city deemed was a timely manner. 

A lien was placed on the property to allow the city to recover demolition costs, potentially through a future sale of the site. The suit alleges that the lien is invalid because an order from a zoning hearing officer is required before a lien can be placed.

Since a portion of the property’s wall collapsed on April 27, sections of Downtown Albuquerque have been closed as officials worked to sequester the debris, voicing concerns about the building harming people or other nearby businesses.

The Bliss Building had been red-tagged and shut down by the city just one week before the building partially collapsed.

On April 30, a structural engineer deemed the property unstable and said it would need to be demolished. The Vatoseows requested a two-week extension on May 15, stating they would perform the demolition themselves.

Roughly one month later, city officials state that the agreement between the Vatoseows and a construction company had “dissolved.” The following day, Code Enforcement sent a letter requesting immediate action to get the demolition back on schedule, though the Vatoseows did not respond.

The lawsuit alleges that the city caused further harm to the building after they “recklessly pulled down the remaining wall and roof,” adding that if the city had hired an engineer and worked with the owners to stabilize the building, it could have been saved and eventually rebuilt.

“The City used heavy equipment to push the debris from the collapsed wall off the sidewalk and into the building and to pull down a section of the wall that had not yet collapsed,” the suit states. “This caused a larger portion of the wall and roof to collapse, which contributed to the building becoming a total loss.”

Additionally, the suit states city officials violated the Inspection of Public Records Act by failing to produce all requested documents relevant to the Bliss Building.

Cadigan said the issue mimics a similar situation that happened in New York City recently, in which thenearly collapsed after a severe structural failure.

He said in that case, however, the city provided aid to the building owners rather than place all the responsibility on them.

"The city came in and they helped the owners stabilize the building,” he said. “They didn't come in and tear it down. They found engineers before they started messing with it.”